13
Total Works
0
In Progress
0
Completed
0
Delayed
0
On Hold
0%
Avg. Progress
Status Breakdown
Works (13)
| Work | Location | Type | Status | Progress | Due |
|---|---|---|---|---|---|
| Yeletitumu To Panta Kalava At Gorripudi | Karapa, Kakinada Rural | Road Contract | Not Started | 0% | — |
| Valasapakalu To Gudarigunta Via Bandagunta | Kakinada (Rural), Kakinada Rural | Road Contract | Not Started | 0% | — |
| Penumarthi To ADB Road | Kakinada (Rural), Kakinada Rural | Road Contract | Not Started | 0% | — |
| Medisettipeta To Mantralavari Toomu At Gorripudi |
By Mandal
Progress Distribution
Activity Over Time
Progress updates logged over time
No data for this selection.
| Karapa, Kakinada Rural |
| Road Contract |
| Not Started |
| 0% |
| — |
| KNF Road To Gurajanapalli Via Penuguduru | Karapa, Kakinada Rural | Road Contract | Not Started | 0% | — |
| KNF Road To Gurajanapalli | Karapa, Kakinada Rural | Road Contract | Not Started | 0% | — |
| KNF Road To Gollapalem Via Kongodu | Karapa, Kakinada Rural | Road Contract | Not Started | 0% | — |
| Gurajanapalli To Bandulavaripeta | Karapa, Kakinada Rural | Road Contract | Not Started | 0% | — |
| Gurajanapalli To Adivipudi | Karapa, Kakinada Rural | Road Contract | Not Started | 0% | — |
| Gorripudi To Lathalovapora | Karapa, Kakinada Rural | Road Contract | Not Started | 0% | — |
| Gorripudi To Gurajanapalli | Karapa, Kakinada Rural | Road Contract | Not Started | 0% | — |
| Aratlakatta To Penugununu On R/S Bund of KMJ Channel | Karapa, Kakinada Rural | Road Contract | Not Started | 0% | — |
| Approach Road To Angativaripeta At Gurajanapalli | Karapa, Kakinada Rural | Road Contract | Not Started | 0% | — |